Easy & Quick Way To Pass Your Any Certification Exam.
Our SAP C_TSCM42_67 dumps are key to get success. More than 80000+ success stories.
Clients Passed SAP C_TSCM42_67 Exam Today
Passing score in Real SAP C_TSCM42_67 Exam
Questions were from our given C_TSCM42_67 dumps
Dumpsspot offers the best C_TSCM42_67 exam dumps that comes with 100% valid questions and answers. With the help of our trained team of professionals, the C_TSCM42_67 Dumps PDF carries the highest quality. Our course pack is affordable and guarantees a 98% to 100% passing rate for exam. Our C_TSCM42_67 test questions are specially designed for people who want to pass the exam in a very short time.
Most of our customers choose Dumpsspot's C_TSCM42_67 study guide that contains questions and answers that help them to pass the exam on the first try. Out of them, many have passed the exam with a passing rate of 98% to 100% by just training online.
Dumpsspot puts the best C_TSCM42_67 Dumps question and answers forward for the students who want to clear the exam in their first go. We provide a guarantee of 100% assurance. You will not have to worry about passing the exam because we are here to take care of that.
You select the master data for production orders via production versions.Which information is contained in a production version?
A. The explosion dates for the routing and BOM
B. The routing and BOM alternatives to be used
C. The default order type to be used
D. The control parameters for selecting routings and BOM
The master data for an in-house production process is to be set up in the SAP ECC system. To do this, you should create a suitable routing that plans for five operations in an initial sequence (10, 20, 30, 40, 50). There should be an option of relocating operations 30 and 40 to a second sequence on other work centers if there are capacity bottlenecks. What sequence type would you use to create the second sequence in the system?
A. Substitute sequence
B. Alternative sequence
C. Parallel sequence
D. Standard sequence
Which functions can be triggered before releasing a production order? (Choose three)
A. Selection of a routing
B. Selection of a BOM
C. Stock determination
D. Confirmation
E. Scheduling
You use a planning time fence and fixing type 1. You receive a customer order with a material availability date within the planning time fence.What do you have to consider in this scenario?
A. Requirements planning considers only changes that are relevant for scheduling within the planning time fence.
B. Planned orders are created within the planning time fence and automatically firmed by requirements planning.
C. The MRP controller cannot create planned orders within the planning time fence.
D. Planned orders that are created by requirements planning are shifted to the end of the planning time fence.
Where can you define the default storage location for the material component of a production order? (Choose three)
A. Routing
B. Production supply area of a work center
C. BOM header (product)
D. Production version (product)
E. Material master (component)